F7009. Warehouse buildings, Gross Floor Area (GFA)
F7009. Warehouse buildings, Gross Floor Area (GFA)
Inside wall 0,5 m
2 / m
2 GFA
            
Inside wall finishing: 1,0 finishing/m
2 GFA.
            
Cost of central heating such as CV boilers and air heaters are included in (56) heat distribution.
| Main element | Description | Specialty | Price per m2 GFA | 
|---|---|---|---|
| (43) Floor finish | Monolith | 11,- | |
| Armor screed | Standard flatness requirement | 30,- | |
| Increased flatness requirement | 38,- | ||
| Mastic asphalt | 48,50 | ||
| Epoxy coating | 35,- | ||
| Polyurethane floor finish | 52,50 | ||
| Magnesiet | 45,50 | ||
| Anhydrite | 22,- | ||
| (51)/(56) Heat generation / heat distribution | Hot water heating | 15 °C | 32,- | 
| Gas heating | 5 °C | 25,- | |
| 15 °C | 15,- | ||
| (61) Central electrical facilities | Safety grounding NEN 1010 | 1,- | |
| Cable ducts and cable trays | 3,- | ||
| Low voltage main distributor | 1,- | ||
| (62) Power supply | Combined light distribution device and power supply | 2,- | |
| Powerplant general | 2,- | ||
| (63) Lighting | Lighting installation | 150 Lux, conventional | 15,- | 
| 250 Lux, conventional | 23,- | ||
| Emergency lighting installation | 2,- | ||
| (64) Communication | Sound installation | 4,- | |
| (65) Security | Fire alarm evacution installation | 7,- | |
| Burglar alarm installation | Simple | 2,- | |
| Hose reel and fire extinguishers | 3,- | ||