F7008. Warehouse buildings, constructed area

F7008. Warehouse buildings, constructed area
Main element Description Specialty Price per per m2 constructed area
(11) Ground works Sod removal and ground filling 10,-
Soil improvement depth 1 m 25,-
depth 2 m 49,50
Land fill height 1 m 27,-
(13) Floor beds Concrete on steel 20 kN/m2 44,50
30 kN/m2 62,50
50 kN/m2 74,-
Concrete piled 20 kN/m2 87,-
30 kN/m2 100,-
50 kN/m2 151,-
Asphalt 30,-
Stelcon precast concrete plate Stelcon, 140 mm 52,50
Floor insulation 16,-
(17) Pile foundation Concrete pile, prefab Floorload 20 kN/m2, length 10 m 19,-
Floorload 20 kN/m2, lenght 18 m 36,50
Floorload 20 kN/m2, length 25 m 47,50
Floorload 30 kN/m2, length 10 m 29,-
Floorload 30 kN/m2, length 18 m 50,50
Floorload 30 kN/m2, length 25 m 67,-
Floorload 50 kN/m2, length 10 m 41,50
Floorload 50 kN/m2, length 18 m 70,-
Floorload 50 kN/m2, length 25 m 94,-