F7002. Production buildings, Gross Floor Area (GFA)
F7002. Production buildings, Gross Floor Area (GFA)
| Main element | Type | Description | Price per m2 GFA | 
|---|---|---|---|
| (22) Interior walls / (32) Interior wall openings | Heavy masonry | 100 mm | 94,- | 
| Light glued | 100 mm | 81,- | |
| Metal posts + finish | 70 mm | 78,- | |
| 100 mm | 82,- | ||
| Metal post wall double plating | 100 mm | 100,- | |
| Demountable system + suwide | 108,- | ||
| Steel system | 190,- | ||
| (28) Main structure | Steel construction | Light | 57,- | 
| Moderate | 83,- | ||
| Heavy | 141,- | ||
| Concrete, prefabricated | 111,- | ||
| (42) Interior wall finish | Facing brickwork | 9,- | |
| Plasterwork + painting | 33,- | ||
| Plasterwork + epoxy coating | 59,- | ||
| Plasterwork + vinyl | 46,50 | ||
| Tiles | Standard | 73,- | |
| Acid resistant | 94,- | ||
| Acoustic cladding | 116,- | ||
| Wooden lining | 111,- | ||
| (43) Floor finish | Monolith | 11,- | |
| Cement deck | With linoleum | 45,- | |
| With carpet | 41,- | ||
| Hardconcrete, heavy | 30,- | ||
| Tiles | Standard | 72,- | |
| Acid resistant | 99,- | ||
| Computer floor | 120,- | ||
| Wooden block flooring | 65,- | ||
| Epoxy floor finish | 35,- | ||
| (45) Ceiling finish | Wood carpentry | 111,- | |
| System ceiling | Mineral wool | 31,- | |
| Aluminum lamella | 62,- | ||
| Integrated | 68,- | ||
| Baffle | 45,- | ||
| (51) Heat generation / (56) Heat distribution | Hot water heating | 18 °C | 51,- | 
| Gas heating | 18 °C | 37,50 | |
| (52) Draining | Rainwater drain | Traditional | 4,- | 
| UV-system | 7,- | ||
| (53) Water | Cold water installation | 3,- | |
| (54) Gasses | Gas installation | 1,- | |
| (57) Air handling | Mechanical ventilation | 43,- | |
| Air supply and air exhaust installation | 101,- | ||
| (61) Central electrical facilities | Safety earthing NEN1010 | 1,- | |
| Cable duct and cable trays | Light industrial | 3,- | |
| Moderate industrial | 7,50 | ||
| Heavy industrial | 11,- | ||
| Low voltage main distributor | Light industrial | 7,50 | |
| Moderate industrial | 12,- | ||
| Heavy industrial | 16,- | ||
| (62) High voltage current | Light distribution unit and power supply | 350 lux | 3,- | 
| 500 - 600 lux | 4,- | ||
| Power distribution unit and power supply | Light industry | 19,- | |
| Moderate industrial | 24,- | ||
| Heavy industrial | 36,50 | ||
| Power plant Power instalaltion | General | 3,- | |
| (63) Lighting | Lighting installation | 350 lux HF | 25,- | 
| 500 - 600 lux HF | 33,50 | ||
| Emergency lighting | 2,- | ||
| (65) Safety | Fire alarm-evacuation installation | 10,- | |
| Burglar alarm | Simple alarm system | 2,- | |
| Hose reel and fire extinguishers | 2,- | ||