F7001. Production buildings, constructed area
F7001. Production buildings, constructed area
The cost of main element (11) earthworks, cut sods is included in the main element (13) floors on foundation.
The cost of main element (11) earthworks, excavating foundation trench is included in the main element (16) foundation construction
Main element | Activity | Description | Price per m2 constructed area |
---|---|---|---|
(11) Earthworks | Sod removal and ground filling | 10,- | |
Soil improvement | depth 1 m | 25,- | |
depth 2 m | 49,50 | ||
Terrain fill | height 1 m | 27,- | |
(13) Non suspended floors at ground level (beds) | Concrete on steel | 20 kN/m2 | 44,50 |
30 kN/m2 | 62,50 | ||
50 kN/m2 | 74,- | ||
Concrete on piles | 20 kN/m2 | 87,- | |
30 kN/m2 | 100,- | ||
50 kN/m2 | 151,- | ||
Asphalt | 30,- | ||
Stelcon precast concrete plate | 140 mm | 52,50 | |
Floor insulation | 16,- | ||
(17) Pile foundation | Concrete pile, prefab | Floorload 20 kN/m2, length 10 m | 19,- |
Floorload 20 kN/m2, lenght 18 m | 36,50 | ||
Floorload 20 kN/m2, length 25 m | 47,50 | ||
Floorload 30 kN/m2, length 10 m | 29,- | ||
Floorload 30 kN/m2, length 18 m | 50,50 | ||
Floorload 30 kN/m2, length 25 m | 67,- | ||
Floorload 50 kN/m2, length 10 m | 41,50 | ||
Floorload 50 kN/m2, length 18 m | 70,- | ||
Floorload 50 kN/m2, length 25 m | 94,- |