F4009. Pile foundations

F4009. Pile foundations

Minimum number of 50 piles.

Inclusive:

  • (revised) calculations, - drawings, piling plan;
  • measuring and setting out;
  • reinforcement and earthing bars;
  • removal of drilling mud and contaminated ground;
  • acoustic measuring;
  • piles cutting and removal of pile cut offs.

Exclusive:

  • excavation and test trenches;
  • dock plates, fencing etc.
Type Specification Price per m
From Till
Prefabricated concrete piles Maximal 290 x 290 mm 31,- 40,-
320 x 320 mm till 380 x 380 mm 43,- 57,-
Minimal 400 x 400 mm 64,- 80,-
Mortar piles Light construction 74,- 90,-
Heavy construction 95,- 116,-
Atlas-/Fundex-/Vibro piles Light construction 85,- 106,-
Heavy construction 111,- 137,-
Tubexpiles 316,- 405,-