F7015. Office buildings, constructed area

F7015. Office buildings, constructed area

The costs of main element (11) bottom protection, excavation foundation are included in the costs of main element (16) foundation construction.

Main element Description Specialty Price per m2 constructed area
(11) Ground works Sod removal and backfilling 10,-
Soil improvement depth 1 m 25,50
depth 2 m 49,-
Land fill height 1 m 27,-
(13) Floor beds Ground floor on sand Thickness 150 mm 39,50
Thickness 200 mm 49,-
Thickness 250 mm 59,-
Insulation layer Thickness 100 mm 12,-
Thickness 150 mm 15,-
Hollow core slab Insulated 88,50
Combination floor Insulated 47,-
(16) Foundation constructions Concrete beam 41,50
Concrete footing With concrete beam 51,-
With brickwork strip 52,-
(17) Pile foundation Concrete pile, prefab 0 - 3 floors, 10 m 32,-
0 - 3 floors, 18 m 47,-
0 - 3 floors, 25 m 105,-
4 - 7 floors, 10 m 45,50
4 - 7 floors, 18 m 70,-
4 - 7 floors, 25 m 115,-
8 - 10 floors, 10 m 62,-
8 - 10 floors, 18 m 96,-
8 - 10 floors, 25 m 126,-