F7015. Office buildings, constructed area
F7015. Office buildings, constructed area
The costs of main element (11) bottom protection, excavation foundation are included in the costs of main element (16) foundation construction.
| Main element | Description | Specialty | Price per m2 constructed area | 
|---|---|---|---|
| (11) Ground works | Sod removal and backfilling | 10,- | |
| Soil improvement | depth 1 m | 25,50 | |
| depth 2 m | 49,- | ||
| Land fill | height 1 m | 27,- | |
| (13) Floor beds | Ground floor on sand | Thickness 150 mm | 39,50 | 
| Thickness 200 mm | 49,- | ||
| Thickness 250 mm | 59,- | ||
| Insulation layer | Thickness 100 mm | 12,- | |
| Thickness 150 mm | 15,- | ||
| Hollow core slab | Insulated | 88,50 | |
| Combination floor | Insulated | 47,- | |
| (16) Foundation constructions | Concrete beam | 41,50 | |
| Concrete footing | With concrete beam | 51,- | |
| With brickwork strip | 52,- | ||
| (17) Pile foundation | Concrete pile, prefab | 0 - 3 floors, 10 m | 32,- | 
| 0 - 3 floors, 18 m | 47,- | ||
| 0 - 3 floors, 25 m | 105,- | ||
| 4 - 7 floors, 10 m | 45,50 | ||
| 4 - 7 floors, 18 m | 70,- | ||
| 4 - 7 floors, 25 m | 115,- | ||
| 8 - 10 floors, 10 m | 62,- | ||
| 8 - 10 floors, 18 m | 96,- | ||
| 8 - 10 floors, 25 m | 126,- | ||