F4016. Main supporting constructions
F4016. Main supporting constructions
Part | Type | Model | Unit | Price per unit | |
---|---|---|---|---|---|
From | Till | ||||
Steel frame | Production building | Single layer | m2 GFA | 110,- | 225,- |
Multi layer | m2 GFA | 255,- | 455,- | ||
Warehouse building | Clear height 7 m | m2 GFA | 110,- | 185,- | |
Office building | Hollow core slabs | m2 GFA | 100,- | 125,- | |
Prefab concrete floorplates | m2 GFA | 110,- | 150,- | ||
Steel frame | Coated | kg | 2,50 | 4,- | |
Galvanized | kg | 3,- | 5,- | ||
Fire resistant spraying | Beams and columns | 60 min. fire resistant | m2 | 81,- | 127,- |
90 min. fire resistant | m2 | 122,- | 188,- | ||
Fire resistant coating | Beams and columns | 60 min. fire resistant | m2 | 51,- | 66,- |
90 min. fire resistant | m2 | 81,- | 112,- | ||
Concrete frame | Poured during construction | m2 GFA | 270,- | 390,- | |
Prefab | m2 GFA | 275,- | 400,- | ||
Concrete wall | Stabilisation wall | m3 | 865,- | 1.075,- | |
Concrete column | Square | m3 | 850,- | 1.250,- | |
Concrete beam | Cantilever beam | m3 | 700,- | 1.200,- |