F4002. Excavations and backfilling
F4002. Excavations and backfilling
Activity | Method | Specification | Price per m3 | |
---|---|---|---|---|
From | Till | |||
Excavation, loading and removal from site | Mechanically | Excavation >1.000 m3 including sampling and landfill cat. 0 | 11,- | 22,- |
Excavation and loading | Mechanically | Excavation >1.000 m3 | 6,10 | 11,70 |
Excavate | Manually | 45,- | 61,50 | |
Dispose of surplus soil | Distance depot 3 km | To depot or on site | 5,80 | 9,80 |
Backfilling | Manually | 22,50 | 31,- | |
Backfilling and compacting | Mechanically | Exclusive delivery soil/sand | 6,- | 12,50 |
Soil supply | From depot on site | 6,- | 12,50 | |
Sand delivery | 16,- | 32,- |