Part | Implementation | Unit | Price per unit | |
---|---|---|---|---|
From | Till | |||
Concrete structures | m3 | 138,- | 340,- | |
Concrete floor | Reinforced | m3 | 48,50 | 80,- |
Concrete plinths | Reinforced | m3 | 192,- | 383,- |
Plain | m3 | 340,- | ||
Masonry | Stretcher bond | m2 | 22,- | 32,- |
Brick bond | m2 | 27,- | 65,- | |
Masonry foundations | m3 | 213,- | ||
Sawing concrete | m | 54,- | 96,- | |
Sawing masonry | m | 16,- | 81,- | |
Tiled floors and walls | m2 | 16,- | 48,- | |
Plasterwork | m2 | 8,- | 27,- | |
Partitions | m2 | 11,- | 30,- | |
Ceilings | m2 | 7,- | 13,- |