A4001. Boiler plants
A4001. Boiler plants
Central
Complete boiler plants.
Included:
- chimney;
- oil facilities;
- boiler house;
- insulation.
Excluded:
- water treatment;
- oil storage;
- piping.
Type | Model | Pressure in bar | Temperature in ºC | Yield in ton/h | Price per ton/h steam | |
---|---|---|---|---|---|---|
From | Till | |||||
Package unit | 30 | 390 | 30 - 80 | 114.600,- | 73.000,- | |
Central | Single unit | 30 | 390 | 100 - 200 | 87.400,- | 66.000,- |
Multiple units | 30 | 390 | 100 - 200 | 132.400,- | 98.600,- | |
Single unit | 100 | 520 | 100 - 200 | 157.700,- | 101.100,- |