F7029. Laboratory buildings, additional
F7029. Laboratory buildings, additional
Main element | Description | Specialty | Unit | Price per unit |
---|---|---|---|---|
(24) Stairs and ramps | Main staircase | Simple | floor | 7.950,00 |
Luxe | floor | 11.800,00 | ||
Emergency staircase | floor | 5.000,00 | ||
(52) Drains | Sludge pit | 5.000 liter | piece | 10.900,00 |
10.000 liter | piece | 15.900,00 | ||
(57) Air treatment | Exhaust system | piece | 7.130,00 | |
(59) | Architectural provisions for mechanical installations | Mechanical installations | % | 6,00 |
(64) Communication | Telephone exchange | Separate system | connection point | 417,00 |
Integrated system | connection point | 481,00 | ||
(65) Security | Electrical sunscreens | Excluding sunscreens | piece | 350,00 |
Emergency shower | piece | 2.007,00 | ||
(66) Transport | People/goods elevator | floor | 20.250,00 | |
(69) | Architectural provisions for electrical installations | Electrical installations | % | 2,00 |
(74) Fixed sanitation facilities | Toilet group | Simple | piece | 17.400,00 |
Luxuray | piece | 24.100,00 | ||
Basement | m2 | 760,00 | ||
(75) Fixed maintenance facility | Window cleaning rail (double) | m circumference | 267,00 | |
Window cleaning installation | piece | 59.300,00 | ||
(78) | Laboratory bench with lower cabinets | Medium | m | 1.585,00 |
Complicated | m | 3.700,00 | ||
Sink with upper cabinets | m | 7.400,00 | ||
Acid fume chamber including facilities | Medium | m | 6.550,00 | |
Complicated | m | 9.827,00 |