F7024. Laboratory buildings, Gross Floor Area (GFA)
F7024. Laboratory buildings, Gross Floor Area (GFA)
Inside wall 0,5 - 0,8 m
2 inside wall / m
2 GFA.
Inside wall finishing 1,0 - 1,6 m
2 inside wall finishing / m
2 GFA.
Cost of heating like CV boilers are included in heat distribution (56).
Main element | Description | Specialty | Price per m2 GFA |
---|---|---|---|
(22) Interior walls / (32) Interior walls openings | Interior wall openings | Masonry | 87,- |
Light glued | 75,- | ||
Metal post wall | 70 mm | 50,- | |
100 mm | 58,- | ||
100 mm, with melamine | 80,- | ||
125 mm | 65,- | ||
125 mm, with plaster/melamine | 90,- | ||
Systeemwanden | Removable with suwide | 100,- | |
50 wall systems, 50 glass wall | 125,- | ||
Removable, steel | 140,- | ||
(42) Interior wall finish | Facing brickwork | 9,- | |
Plasterwork | 18,- | ||
Decorative plaster | 37,50 | ||
Painting | 13,- | ||
Wallpaper | 18,- | ||
Wallcovering | Textile | 25,- | |
Wall tiles | Standard, including jointing | 70,- | |
Acid resistant | 92,50 | ||
Epoxycoating | With fine sanding | 58,- | |
(43) Floor finish | Cement deck | With linoleum | 45,- |
With carpet | 41,- | ||
PVC, chemically resistant | 43,- | ||
Epoxycoating | 50,- | ||
With epoxy mortar floor | 53,- | ||
Computer floor | 120,- | ||
Tiled floor | Double fired | 66,- | |
Ceramic | 80,- | ||
Acid resistant | 154,- | ||
Earthing floor | 15,- | ||
(45) Ceiling finish | Wood carpentry | 97,- | |
System ceiling | Mineral wool tiles 600 x 600 mm | 31,- | |
Mineralwool tiles 600 x 1.200 mm | 30,- | ||
Sag tile 600 x 600 mm | 35,- | ||
Horizontal lamellea | 62,- | ||
Vertical lamellea | 67,- | ||
Integrated steel | 69,- | ||
(51) Heat generation / (56) Heat distribution | Boiler | VR/HR, including gas pipelines | 24,- |
(52) Draining | Rainwater drains | 8,- | |
Internal sewer system | 13,- | ||
(53) Water | Cold water installation | 12,- | |
Hot water installation, decentralized | 3,- | ||
Process water | 31,- | ||
(54) Gasses | Compressed air | 13,- | |
Vacuum | 12,- | ||
Nitrogen/oxygen | Stainless steel RVS piping network per type of gas | 47,- | |
Steel piping network per type of gas | 15,- | ||
(56) Heat distribution | Pipes | With induction units | 129,- |
With radiators | 49,- | ||
With convectors | 67,- | ||
(57) Air treatment | Ventilation | Standard | 137,- |
Limited cooling | 216,- | ||
Extensive cooling | 254,- | ||
(61) Central electrical facilities | Safety grounding NEN 1010 | 1,- | |
Cable duct and cable trays | 9,- | ||
Wall conduits | 10,- | ||
Low voltage main distributor | With overload protection | 18,- | |
(62) Power current | Combination junction devices | With supply lines (extensive) | 13,- |
Supply lines | Supply lines for WTB and elevator instalaltions | 6,- | |
Powerplant | 6,- | ||
(63) Lighting | Lighting fixture | Conventional | 40,- |
High-frequent | 45,- | ||
Combined light wall outlets endgroup installation | 3 wall outlets per workplace | 23,- | |
Emergency lighting | Decentral (batteries) | 5,50 | |
(64) Communication | Paging system | Wired | 2,- |
Telephone/data system, integrated | Empty pipe installation | 2,- | |
Wired | 34,- | ||
(65) Security | Fire extinguishers | Reel and fire extinguishers | 3,- |
Fire alarm and evacuation installation | Escape route detection, limited | 10,- | |
Extensive escape route detection | 18,- | ||
Burglar alarm | Simple | 6,- | |
Dry extinguisher line | 4,- | ||
(67) Building management system | Control and signal system of mechanical and electrical installations | 6,- |