F7024. Laboratory buildings, Gross Floor Area (GFA)
F7024. Laboratory buildings, Gross Floor Area (GFA)
Inside wall 0,5 - 0,8 m
2 inside wall / m
2 GFA.
            
Inside wall finishing 1,0 - 1,6 m
2 inside wall finishing / m
2 GFA.
            
Cost of heating like CV boilers are included in heat distribution (56).
| Main element | Description | Specialty | Price per m2 GFA | 
|---|---|---|---|
| (22) Interior walls / (32) Interior walls openings | Interior wall openings | Masonry | 87,- | 
| Light glued | 75,- | ||
| Metal post wall | 70 mm | 50,- | |
| 100 mm | 58,- | ||
| 100 mm, with melamine | 80,- | ||
| 125 mm | 65,- | ||
| 125 mm, with plaster/melamine | 90,- | ||
| Systeemwanden | Removable with suwide | 100,- | |
| 50 wall systems, 50 glass wall | 125,- | ||
| Removable, steel | 140,- | ||
| (42) Interior wall finish | Facing brickwork | 9,- | |
| Plasterwork | 18,- | ||
| Decorative plaster | 37,50 | ||
| Painting | 13,- | ||
| Wallpaper | 18,- | ||
| Wallcovering | Textile | 25,- | |
| Wall tiles | Standard, including jointing | 70,- | |
| Acid resistant | 92,50 | ||
| Epoxycoating | With fine sanding | 58,- | |
| (43) Floor finish | Cement deck | With linoleum | 45,- | 
| With carpet | 41,- | ||
| PVC, chemically resistant | 43,- | ||
| Epoxycoating | 50,- | ||
| With epoxy mortar floor | 53,- | ||
| Computer floor | 120,- | ||
| Tiled floor | Double fired | 66,- | |
| Ceramic | 80,- | ||
| Acid resistant | 154,- | ||
| Earthing floor | 15,- | ||
| (45) Ceiling finish | Wood carpentry | 97,- | |
| System ceiling | Mineral wool tiles 600 x 600 mm | 31,- | |
| Mineralwool tiles 600 x 1.200 mm | 30,- | ||
| Sag tile 600 x 600 mm | 35,- | ||
| Horizontal lamellea | 62,- | ||
| Vertical lamellea | 67,- | ||
| Integrated steel | 69,- | ||
| (51) Heat generation / (56) Heat distribution | Boiler | VR/HR, including gas pipelines | 24,- | 
| (52) Draining | Rainwater drains | 8,- | |
| Internal sewer system | 13,- | ||
| (53) Water | Cold water installation | 12,- | |
| Hot water installation, decentralized | 3,- | ||
| Process water | 31,- | ||
| (54) Gasses | Compressed air | 13,- | |
| Vacuum | 12,- | ||
| Nitrogen/oxygen | Stainless steel RVS piping network per type of gas | 47,- | |
| Steel piping network per type of gas | 15,- | ||
| (56) Heat distribution | Pipes | With induction units | 129,- | 
| With radiators | 49,- | ||
| With convectors | 67,- | ||
| (57) Air treatment | Ventilation | Standard | 137,- | 
| Limited cooling | 216,- | ||
| Extensive cooling | 254,- | ||
| (61) Central electrical facilities | Safety grounding NEN 1010 | 1,- | |
| Cable duct and cable trays | 9,- | ||
| Wall conduits | 10,- | ||
| Low voltage main distributor | With overload protection | 18,- | |
| (62) Power current | Combination junction devices | With supply lines (extensive) | 13,- | 
| Supply lines | Supply lines for WTB and elevator instalaltions | 6,- | |
| Powerplant | 6,- | ||
| (63) Lighting | Lighting fixture | Conventional | 40,- | 
| High-frequent | 45,- | ||
| Combined light wall outlets endgroup installation | 3 wall outlets per workplace | 23,- | |
| Emergency lighting | Decentral (batteries) | 5,50 | |
| (64) Communication | Paging system | Wired | 2,- | 
| Telephone/data system, integrated | Empty pipe installation | 2,- | |
| Wired | 34,- | ||
| (65) Security | Fire extinguishers | Reel and fire extinguishers | 3,- | 
| Fire alarm and evacuation installation | Escape route detection, limited | 10,- | |
| Extensive escape route detection | 18,- | ||
| Burglar alarm | Simple | 6,- | |
| Dry extinguisher line | 4,- | ||
| (67) Building management system | Control and signal system of mechanical and electrical installations | 6,- | |