F7015. Office buildings, constructed area
F7015. Office buildings, constructed area
The costs of main element (11) bottom protection, excavation foundation are included in the costs of main element (16) foundation construction.
Main element | Description | Specialty | Price per m2 constructed area |
---|---|---|---|
(11) Ground works | Sod removal and backfilling | 10,- | |
Soil improvement | depth 1 m | 25,50 | |
depth 2 m | 49,- | ||
Land fill | height 1 m | 27,- | |
(13) Floor beds | Ground floor on sand | Thickness 150 mm | 39,50 |
Thickness 200 mm | 49,- | ||
Thickness 250 mm | 59,- | ||
Insulation layer | Thickness 100 mm | 12,- | |
Thickness 150 mm | 15,- | ||
Hollow core slab | Insulated | 88,50 | |
Combination floor | Insulated | 47,- | |
(16) Foundation constructions | Concrete beam | 41,50 | |
Concrete footing | With concrete beam | 51,- | |
With brickwork strip | 52,- | ||
(17) Pile foundation | Concrete pile, prefab | 0 - 3 floors, 10 m | 32,- |
0 - 3 floors, 18 m | 47,- | ||
0 - 3 floors, 25 m | 105,- | ||
4 - 7 floors, 10 m | 45,50 | ||
4 - 7 floors, 18 m | 70,- | ||
4 - 7 floors, 25 m | 115,- | ||
8 - 10 floors, 10 m | 62,- | ||
8 - 10 floors, 18 m | 96,- | ||
8 - 10 floors, 25 m | 126,- |