F3010. Demolish by hand and wrecking hammer

F3010. Demolish by hand and wrecking hammer

Inclusive:

  • transport of debris.

Exclusive:

  • dumping costs;
  • waste treatment;
  • profit on released material.
Part Implementation Unit Price per unit
From Till
Concrete structures m3 138,- 340,-
Concrete floor Reinforced m3 48,50 80,-
Concrete plinths Reinforced m3 192,- 383,-
Plain m3 340,-
Masonry Stretcher bond m2 22,- 32,-
Brick bond m2 27,- 65,-
Masonry foundations m3 213,-
Sawing concrete m 54,- 96,-
Sawing masonry m 16,- 81,-
Tiled floors and walls m2 16,- 48,-
Plasterwork m2 8,- 27,-
Partitions m2 11,- 30,-
Ceilings m2 7,- 13,-