F3003. Industrial scaffolding

F3003. Industrial scaffolding

Scaffolding for industrial work in accordance with DACE norms.

Remarks

Costs are applicable for 0 - 15 meter and a minimum quantity of 25 m
3.

See H2002: Correction factors for calculations of DACE norms, chapter General.

Exclusive:

  • replacement of disapproved material and lost material;
  • transport cost to and from site.

Inclusive:

  • installation;
  • dismantling.
Activity Unit Price per unit
From Till
Rent m3/week 0,40 0,65
Assembly/dismantling standing scaffold m3 8,-
Assembly/dismantling hanging scaffold m3 14,-
Assembly/dismantling extended scaffold m3 14,-
Assembly/dismantling rolling scaffold m3 11,50