F3003. Industrial scaffolding
F3003. Industrial scaffolding
Scaffolding for industrial work in accordance with DACE norms.
Costs are applicable for 0 - 15 meter and a minimum quantity of 25 m
3.
See H2002: Correction factors for calculations of DACE norms, chapter General.
Exclusive:
- replacement of disapproved material and lost material;
- transport cost to and from site.
Inclusive:
- installation;
- dismantling.
Activity | Unit | Price per unit | |
---|---|---|---|
From | Till | ||
Rent | m3/week | 0,40 | 0,65 |
Assembly/dismantling standing scaffold | m3 | 8,- | |
Assembly/dismantling hanging scaffold | m3 | 14,- | |
Assembly/dismantling extended scaffold | m3 | 14,- | |
Assembly/dismantling rolling scaffold | m3 | 11,50 |