B4001. Complete assembled underground piping system
B4001. Complete assembled underground piping system
Prices are based on a length of at least 10 km in a relatively open outside infrastructure.
Prices are strongly influenced by:
- depth;
- geography;
- soil type;
- number of road and water crossings;
- insulation;
- working pressure;
- agriculture and land situation;
- material prices.
Included:
- indirect costs (construction management), general overhead cost;
- design (pressure 60 Bar, temperature 50 °C, no thermal insulation);
- compensation of land owners and land users;
- materials and erection;
- testing and commissioning;
- temporary building facilities;
- small road- and water crossings (2 drills of 400 meter each);
- ground cover 1,25 meter.
Excluded:
- large river-, channel- and road crossings;
- PIG launcher, receiving station and block valves;
- licences and tax;
- owners internal costs.
Diameter in inches | Price per m CS | Price per m duplex | ||
---|---|---|---|---|
From | Till | From | Till | |
4 | 234,- | 440,- | 135,- | 600,- |
6 | 278,- | 520,- | 462,- | 855,- |
8 | 320,- | 610,- | 600,- | 1.120,- |
10 | 375,- | 685,- | 725,- | 1.380,- |
12 | 420,- | 780,- | 890,- | 1.670,- |
16 | 430,- | 810,- | ||
20 | 460,- | 840,- | ||
24 | 550,- | 1.020,- | ||
30 | 710,- | 1.330,- | ||
36 | 940,- | 1.750,- |